Wings A, B & C – Milestone Release On Commencement of Painting 7 to 13 Floor
Mar 2025

DRAG
Wings A, B & C – Milestone Release On Commencement of Painting 7 to 13 Floor
Mar 2025
Wings A, B & C – Milestone Release On Commencement of Painting 7 to 13 Floor
Mar 2025
Wing B – Milestone Release On Casting of 12th Floor Slab
Mar 2025
Wing A – Milestone Release On Casting of 12th Floor Slab
Mar 2025
Wing A - Pour 1 - 13th floor wall reinforcement work in progress. Pour 2 - 11th floor wall reinforcement work in progress
Feb 2025
Wing B - Pour 3 - 11th floor wall reinforcement work in progress. Pour 4 - 11th floor wall reinforcement work in progress
Feb 2025
Wing C - Pour 5 - 9th floor wall reinforcement work in progress. Pour 6 - 12th floor wall shuttering work in progress
Feb 2025
Non tower Area Podium area structure work in progress
Feb 2025
Tiling works Wing A - 5th floor work in progress
Wing B - 4th floor work in progress. Wing C - 4th floor work in progress
Feb 2025
Painting works. Wing A - 5th floor work in progress. Wing B - 5th floor work in progress. Wing C - 5th floor work in progress
Feb 2025
OWC slab shuttering and reinforcement, retaining wall work in progress
Feb 2025
Wing C – Milestone Release On Casting of Eighth Floor Slab
Mar 2025
Wing A
Jan 2025
Wing B
Jan 2025
Wing C
Jan 2025
Non tower Area -Podium area structure work in progress
Jan 2025
Tiling work in progress
Jan 2025
Painting work in progress
Jan 2025
Wing B – Milestone Release On Casting of Eighth Floor Slab
Jan 2025
Wing B – Milestone Release On Commencement of Painting 1 to 6 Floor
Jan 2025
Wing A – Milestone Release On Casting of Eighth Floor Slab
Jan 2025
Wing C – Milestone Release On Casting of Fourth Floor Slab and Flooring 1 to 6 Floor
Dec 2024
Wing C – Milestone Release On Casting of Fourth Floor Slab and Flooring 1 to 6 Floor
Dec 2024
Wing A – Milestone Release On Commencement of Painting 1 to 6 Floor
Dec 2024
Wing B – Milestone Release On Commencement of Flooring 1 to 6 Floor
Dec 2024