Wing A - Pour 1;6th - 7th floor slab shuttering work in progress. Pour 2;3rd 4th floor reinforcement work in progress
Sep 2024
DRAG
Wing B - Pour 3;3rd - 4th floor slab completed. Pour4;2nd -3rd floor walls and beams reinforcement work in progress
Sep 2024
Wing C - Pour 5;1st - 2nd floor wall shuttering work in progress. Pour 6;2nd 3rd floor reinforcement and shuttering work in progress
Sep 2024
Non tower area - STP structural work completed. Podium area structure work in progress
Sep 2024
Wing A - Pour 1 - 5th Floor Slab Reinforcement Work in Progress
Aug 2024
Wing B - Pour 3 - 3rd Floor Slab Reinforcement Work in Progress and Pour 4 - 2nd Floor Slab Shuttering Work in Progress.
Aug 2024
Wing C – Pour 5 - 2nd Floor Wall Shuttering Work in Progress and Pour 6 - 2nd Floor Wall and Slab Shuttering Work in Progress.
Aug 2024
Non tower area - STP structural work completed. Podium area structure work in progress
Aug 2024
Wing A – Milestone Release On Casting of Fourth Floor Slab
Aug 2024