Overall View - Structure -530/530 Flats completed
Mar 2025

DRAG
East Wing
Mar 2025
South Wing
Mar 2025
West Wing
Mar 2025
East ,South and West wing External Painting works Started
Mar 2025
Basement Painting and Services WIP
Mar 2025
Terrace Waterproofing Works is completed
Mar 2025
Terrace Clay tile fixing work is in progress
Mar 2025
Tiling Work In Progress (530/530 Flats Completed)
Mar 2025
Painting work in progress (530/530 Flats primer completed)
Mar 2025
Windows and Doors fixing work in progress
Mar 2025
Finishing Work in Progress. QA Certification – 274/530 completed
Mar 2025
STP HVAC duct and Plumbing Work is in progress
Mar 2025
Corridor and Staircase Flooring and Painting Completed
Mar 2025
PHE shaft door fixing is completed
Mar 2025
East face( between E and D tower) driveway and car parking work is completed
Mar 2025
Podium Central Courtyard Area Hardscape and Softscape WIP
Mar 2025
Overall View - Structure -530/530 Flats completed
Feb 2025
East Wing
Feb 2025
South Wing
Feb 2025
West Wing
Feb 2025
East ,South and West wing External Painting works Started
Feb 2025
Basement Painting and Services WIP
Feb 2025
Terrace Waterproofing Works is completed
Feb 2025
Terrace Clay tile fixing work is in progress
Feb 2025
Tiling Work In Progress (530/530 Flats Completed)
Feb 2025
Painting work in progress (530/530 Flats primer completed)
Feb 2025
Windows and Doors fixing work in progress
Feb 2025
Finishing Work in Progress. QA Certification – 225/530 completed
Feb 2025
Corridor and Staircase Flooring and Painting Completed
Feb 2025
Podium Central Courtyard Area Hardscape and Softscape WIP
Feb 2025
Overview Structure -530/530 Flats completed
Jan 2025
East Wing
Jan 2025
South Wing
Jan 2025
West Wing
Jan 2025
East, South and West wing External Painting works Started
Jan 2025
Basement Painting and Services WIP
Jan 2025
Terrace Waterproofing Works is completed
Jan 2025
Terrace Clay tile fixing work is in progress
Jan 2025
Tiling Work In Progress (529/530 Flats Completed)
Jan 2025
Painting work in progress (506/530 Flats primer completed)
Jan 2025
Windows and Doors fixing work in progress
Jan 2025
Finishing Work in Progress. QA Certification – 214/530 completed
Jan 2025
Corridor and Staircase Flooring and Painting WIP
Jan 2025
Podium Central Courtyard Area Hardscape and Softscape WIP
Jan 2025